Moorebank Unit Relocation
The Australian Government consolidated and upgraded the Holsworthy Barracks. As part of the upgrade, units based at Moorebank will move to new, purpose-built facilities at the base. The MUR Project involves relocating the School of Military Engineering (SME) and other Defence Units to a new home at Holsworthy
Athassel Civil was engaged by John Holland
The scope of works included
- Installing 4kms of stormwater pipe up to 5m deep
- Installing 5 GPTs up to 5 m deep
- Install approximately 140 precast pits
The complexities of the job included working in a live army base, around live traffic, pedestrian management, working in and around other utilities
Project Info
Client: John Holland
Description: Athassel Civil was engaged by John Holland